PROJECT DETAILS
Place of Application: Oil Field Damborice, Oil Field Borkovany
Cleaning Technology: Downhole equipment preventive cleaning (rod string and tubing) with DIR-X (during production) – usually 2-3 wells in a row
10 – 15 Wells are preventively cleaned twice / three times per year from 2015 to date
Well Parameters
Wells: depth 1 700 – 2 200 m, reservoir temperature 48 – 55°C, pump setting depths 1 400 – 1 900 m, there were a problem with paraffin deposits
Standard cleaning method: once a month hot oiling (with 30 – 38 m3 of hot oil). Usual time between the failures was 12 – 18 months. Workover / intervention required (4 – 5 day): pull the rod pump with rod string and tubing out of the hole, cleaning with steam from paraffin at the surface, casing cleaning with the scraper.
Cleaning Process – Heating up the downhole completion during production
Mixture quantity: 4.8 – 6 m3 per well
Cleaning time: 2 hours per well
Process:
- each well is connected to the central pipe line system (gathering station)
- pump DIR-X (4.8 – 6 m3) down the annulus
- the chemical reaction is divided into four / five time periods (depends on the expected paraffin deposits depth)
- after the reaction brake (5 – 10 minutes), pump 2 – 10 m3 of oil down the annulus to wash out the spent DIR-X with melted paraffin deposits out of the well
- oil pumping did not have to be interrupted during the cleaning process with DIR-X solution
Identical procedure was applied for each well.
Result of Cleaning
Well cleaning with DIR-X is currently performed twice / three times per year. The run life – interval between failures – was increased from 12- 18 months to 42 – 48 months.
DIR-X solution is preferring cleaning method for wells with paraffin issue.
Figure 1 Three wells cleaning in a row – temperature profile at the wellhead
Figure 2 Three wells cleaning in a row – pump truck